Leshka Project

CONSTRUCTION OF THE MYNTDU LESHKA HYDRO ELECTRIC PROJECT
(2 x 42 + 1 x 42) MEGA
WATTS

Status of Works of Myntdu Leshka HE Project

INTRODUCTION

The Myntdu Leshka Hydro Electric Project (2 x 42 + 1 x 42) MW is a Run Off River (ROR) Scheme, located at the Jaintia Hills District of the State of Meghalaya . The project envisages construction of the 63 meters’ height dam across the Myntdu River , just below the tri junction of its two other tributaries, the Lamu and the Umshariang. The impounded water is to be conducted to the Power House through a 3313.46 meters’ long and 3.4 meters’ diameter HRT, a 314 meters’ long HPT and 731.25 meters’  long Penstock. The water after generation will be discharged into the Lyngriang river, which is another tributary of the Myntdu (downstream). The conductor system also include an intake shaft gate and a 85 meters’ deep & 8 meters’ diameter Surge Shaft and a Butterfly valve. Recently, due to severe power crisis in the State, it was decided to tap all available potential in the form of Renovation & Modernization and Upgradation (Stages I & II) and addition of another unit of 42 MW in the 2 x 42 Mega Watts’ Project, using the same Dam, the same water conductor system and the same Power House. The capacity of the Surge Shaft & Intake Gate have been modified to suit the water flow forces to 3 (three) units. Three penstock pipes have now been proposed to conduct the water to the 3 (three) Turbines at the Power house.  

The investigation work of the Myntdu Leshka Stage I Hydro Electric Project (2 x 42) MW was taken up by the Board during 1975-76 and the final Revised Detailed Project report (DPR) was submitted to the Central Electricity Authority (CEA) for clearance, in October 1998. The public hearing for Environmental Clearance conducted by the Meghalaya Pollution Control Board (MPCB) was held in March 1999, of which public has welcomed the Project. Necessary site clearance from the Ministry of Environmental and Forests (MOEF) to take up the pre construction works of the Project was given in August 1999. The Techno Economic Clearance (TEC) was issued by the CEA vide letter No.2/Meg/2/99-PAC/9499-9522/702 Dt. 20th September 1999 . The necessary Forest Clearance, subject to certain conditions, has been accorded by the MOEF vide their letter No.8-33/2000-FC dated 19.6.2001. The MOEF accorded Environmental Clearance vide Notification Ref.No.J-12011/4/99-IA- Dt.20/9/2001. The Meghalaya State Electricity Board accorded Administrative Approval for the construction of the 2 x 42 MW  Project vide Board’s Letter No.U/o No.GAP/258/97/vol.I/152 Dt.12/6/02 with a total project cost of Rs 363.08 Crores, including the Interest During Construction (IDC). While the provisional clearance was received in June 2002, the final clearance was accorded in May 2004.  

At present, the work on the first 2 (two) units is in an advance stage of completion, while works on the 3rd Unit also have started.

The project completion schedule is as below:-

Major Works Time of Completion
DAM                                             February 2009
TUNNEL February 2009
SURGE SHAFT February 2009
PENSTOCK & PIPE LINER March / April 2009
POWER HOUSE (CIVIL) April / May 2009
POWER HOUSE (ELECTRICAL) April / May 2009

The commissioning & commercial operation dates are as follows:

Commissioning Commercial Operation
UNIT I May 2009 June 2009
UNIT II June 2009 July   2009

The delay in completion and commissioning of the Project are due to many reasons, the main one being due to continuous rainfall experienced in the Project site (as the Project area is located in the southern slope of the State and it is in the same belt with Cherrapunjee) and also due to the geological condition in the Project.  

The rain affected the work at the dam which started since May, 2004.  Hence the work had to be stopped and it was restarted from October 2004 onwards. However the work for the dam was disrupted again by rain in 2005-2006 and 2007  and in 2007-2008 the work at the power house got badly affected with a sudden flood in April 2008, thereby halting the work.  It may be mentioned that both the works involve working below river bed level and hence rain is bound to disrupt the work. However the work at HPT has not been much affected since it is above the river bed level. The rainfall at the Project site lasted for about six months.  

On completion, the Project would generate about 372.69 Million Units of Electricity annually from the first two Units. The estimated cost at 1999 price level is Rs.363.08 Crores and the revised Cost at 2006 price level is Rs.671.29 Crores, inclusive of the Interest During Construction (IDC).

SALIENT FEATURES OF THE PROJECT  

A.     DAM

Sl. No.

Description of Work

TEC (1999)

Current (2007)

1.

Type

Concrete Gravity

Concrete Gravity

2

Live Storage

7.32M Cubic meters

7.32M Cubic meters
(141.8 X 106M3

3

FRL

618.00 meters

618.00 meters

4

MDDL

606.15 meters

606.15 meters

5

Bed Level

563.00 meters

561.00 meters

6

Length:

(i) Overflow
(ii) Non-Overflow

 

103.75 meters
187.00 meters

 

107.50 meters
212.10 meters

7

Deepest Foundation Level

561.00 meters

557.00 meters

8

Crest Level

597.00 meters

587.50 meters

9

Maximum Height

59.00 meters

63.00 meters

10

Top of Non-overflow section

620.00 meters

620.00 meters

11

Excavation

1.43 Lakh M3

6.73 Lakh M3

12

Concreting

2.04 Lakh M3

3.33 Lakh M3

13

Spillway Capacity

12000 Cumecs

10,440 Cumecs

14

Gates (Sluices)

5 (five) Nos

7 (seven) Nos.

15

Gate Size

16.75 meters x 17.00 meters

8.00 meters x 12.55 meters

B.  HRT Intake :  

Sl. No.

Description of Work

TEC (1999)

Current (2007)

1

Type

Semi-circular with trash rack.

Semi-circular with trash rack.

2

Control

Fixed wheel gate operated through shaft.

Fixed wheel gate operated through shaft.

3

Inlet elevation

601.41 meters

599.55 meters

C. LOW PRESSURE Tunnel:  

Sl. No.

Description of Work

TEC (1999)

Current (2007)

1

Type

Circular

Circular

2

Length

3667.00 meters

3313.46 meters

3

Diameter

3.40 meters

3.40 meters (Modified Horse shoe)

4

Design Discharge

30.094 cumecs

30.094 cumecs

5

Velocity

3.21 meters /Second

3.21 meters /Second

D. SURGE TANK:  

Sl. No.

Description of Work

TEC (1999)

Current (2007)

1

Type

Restricted Orifice

Restricted Orifice

2

Height

63.50 meters

85.00 meters

3

Diameter

8.00 meters

8.80 meters

E. HIGH PRESSURE TUNNEL:  

Sl. No.

Description of Work

TEC (1999)

Current (2007)

1

No.

1 (one)

1 (one)

2

Type

Circular,steel lined

Circular,steel lined

3

Diameter of Pipe

2.60 meters’ diameter

2.80 meters’ diameter

4

Length

245.00 meters

314.00 meters

F. PENSTOCK :

Sl. No.

Description of Work

TEC (1999)

Current (2007)

1

Number

1 (one)

Two Nos from Butterfly Valve to power house

2

Diameter

2.60 meters

2.00 meters

3

Length

825.00 meters

731.25 meters

G. POWER HOUSE:

Sl. No.

Description of Work

TEC (1999)

Current (2007)

1

Type

Overground

Surface Power House

2

Size

34.40 x 21.80

54.70 X25.50 meters

3

Gross head

334.00 meters

334.00 meters

4

Average Net Head

316.16 meters

316.16 meters

5

Type of Turbine

Francis-V Shaft

Francis-V Shaft

6

Rotational Speed

750 rpm

500/600RPM

7

C.L.of distributor level

276.20 meters

282.00

8

Generator Floor Level

285.00 meters

289.50 meters

9

Maximum T.W.L.

284.30 meters

295.29 meters

10

Normal T.W.L.

284.00 meters

288.18

11

Minimum T.W.L.

281.40 meters

286.78 meters

CHRONOLOGY OF EVENTS

The following tables indicate the important Chronology of events  : 

Events

1975-1979 Starting year for the investigation work of the Project
August 1997 Initial Detailed Project Report with 3 x 18 Mega Watts’ capacity submitted to Central Electricity Authority (CEA) for Techno Economic Clearance (TEC)
1997 The Central Electricity Authority recommended 2 x 42 Mega Watts ’ Installed Capacity
October 1998 MeSEB submitted revised Detailed Project Report
March 1998 Public Hearing Committee conducted by the Meghalaya Pollution Control Board at Amlarem & Khliehriat
September 1999 Techno Economic Clearance (TEC) was obtained (with five years tenure of completion)
September 2001 Provisional environmental/ site clearance obtained
June 2002 Provisional Forest Clearance obtained
June 2002 MeSEB’s Administrative approval obtained
25th October 2002 Foundation stone laid by President of India
May 2004 Final Forest Clearance was received
The Project works started thereafter, but due to heavy rainfall in the year, the works started in full swing only in October, 2004

    

 

Date of starting of works Name of works
May 2004  Dam
February 2005 Tunnel
February 2006 Power House (civil)
January 2006 Power House (E & M). Components of E & M items are at different stages of procurement, fabrication & erection.
May 2007 Penstock
December 2007 Switchyard

A BIRD EYE VIEW OF THE DAM UNDER CONSTRUCTION

SPECIAL FEATURES OF THE PROJECT

1.   Acidity of the Myntdu river:

The pH value of the Myntdu River is around 4.00. The cause of acidity is due to coal mining in the catchment area. The coal mining is privately owned and is done unscientifically. It is known that the acid water corrodes steel and is disastrous toconcrete. While designing various structures, the environment for concrete and steel has been considered as extremely aggressive. Anti corrosion steel & stain less Steel has to be used in structures. In addition, micro silica & other admixtures have to be added in the concrete to make it more durable and dense.

2.   Rainfall:

The Project area is located in the southern slopes of the State and is in the same belt with Cherrapunjee, which receives the   heaviest rainfall in the world. Due to heavy rainfall, the project schedule had to be rescheduled many times.     

3.   Seismicity:

The project area is located very close to the Dawki fault. Dawki fault, according to seismologist, has potential to generate earthquake measuring 9+ in the Richter scale. In order to ensure stability, all structures have been appropriately designed to withstand 9+ earthquake impact.  

4.   Diversion system:

No Diversion Tunnel has been provided. The water has been diverted through the river using divider wall upstream and downstream coffer dam.

PROGRESS REPORT ON THE CONSTRUCTION OF THE MYNTDU LESHKA HYDRO ELECTRIC PROJECT, AS ON 31 MARCH 2009  

A.     FINANCIAL STATUS:  

1.      Sanctioned Cost (with base year):  Rs 363.08 Crores, as per 1999 price index (Including IDC*)

2.      Latest Cost (with base year) :   Rs 671.29 Crores, as per 2005 price index (Including IDC*)

3.      Electricity cost (Rs/ Kilowatt hour) :  Rs 2.68  

4.      Debt : Equity Ratio;    70 : 30  

5.      Details of Debt to be raised & equity details : A loan has been arranged from the Rural Electrification Corporation Ltd and market bonds. 

6.  Foreign currency loan (if any):    Does not arise.  

7.  Expenditure up to end of previous financial year : Rs 423.74 Crores (up to 31st March 2008 ).  

8.   Expenditure during Current year (From 1st April’08 upto 31st March 2009 ):  Rs 263.63 Crores
     
(Including IDC)                                                                                                            

*Interest During Construction

A.             PHYSICAL STATUS:  

  1. CIVIL / HYDRO MECHANICAL WORKS

  2. ELECTRO MECHANICAL WORKS

  3. RECEIPT OF PLANT AND EQUIPMENT

COMMISSIONING ACTIVITIES:

Sl. No.

Items of works

Schedule date

Actual date (Present Revised)

1.

Civil Works

  1. Dam/Barrage

  2. Water/Conductor System (HRT)

  3. Power House civil works

  4. Tail Race works

  5. Penstock

 

March 2007
March 2007

March 2007
March 2007
March 2007

 

Feb’09-1st Stage & June’ 09 Final Stage
April 2009

August 2009
August 2009
August 2009

2

Electrical/Mechanical works

  1. Generating Units

  2. Main step up Transformers

  3. Switchyard

  4. EOT Crane

  5. Butterfly Valve

  6. LCTAC  Switchgear

  7. DCDB Battery Banks

  8. DG .Set

  9. Power House Lift

  10. Illumination system

  11. Communication system

  12. Ventilation system

  13. Fire fighting system

 

 Nov/08
Nov/08

Nov/08
June/08
Oct/08
Oct/08
Oct/Nov/08
Oct/08
Oct/08
Oct/Nov/08
Nov/Dec/08
Dec/08
Dec/08

 

   

The 1st Unit is expected to be commissioned in September, 2009,  the 2nd Unit in November 2009 and the 3rd Unit in June 2010.

PROJECT OVERALL PROGRESS:  

Date of Approval (Latest)

Expected date of commissioning

Remarks/Reasons of Slippages

 

May/04 (From the Ministry of Environment & Forest)

September 2009 for Unit-I
November 2009 for Unit-II

Delay in receipt of MOEF clearance, extra quantity of work, rainfall, drawings.

 

 

 

COST/EXPENDITURE:  

Latest approval cost (Including IDC)

Cumulative Expenditure up to 31st March 2008

Cumulative Expenditure in the year of 2008 – 09 up to 31st March 2009 (Including IDC)

Rs.671.29* Crores (As per 2006 price level) including IDC

Rs.423.74 Crores

Rs.263.66 Crores (Provisional)

* Amount to be revised with the increase in cost due to extra quantity of works & etc.


A VIEW OF TUNNEL WORK UNDER CONSTRUCTION